Deliverables of the project

this is a view of all the planned deliverables, use the button to change it


(Contents)

Quality assurance procedures

WP011
Content Quality assurance procedures: a document about the data exchange protocol (software tools to produce documents, formats, rules of distribution, ..) between the partners and methodologies to be used in the activities in order to assure quality.
Due date 01/03/1999 Release date 06/03/1999
Document../../files/OF011-001-Qualityassuranceplanenea.zip

(Contents)

Communication tools enabled

WP011
Content WEB site of Ishtar: the site is organised with a public access level, used to present and promote the project and a restricted access level containing the repository of the documents to be exchanged (up/download) between the partners. Mailing list of Ishtar: a mailing list that simplifies the connection between the partners Templates for documents: templates for different kinds of documents in order to easily classify and manage them.
Due date 01/03/1999 Release date 03/06/1999
Document../../files/OF011-001-Qualityassuranceplanenea.zip
Other linkhttp://spring.bologna.enea.it/ishtar
Other link2mailto://ishtar@bologna.enea.it

(Contents)

Document about the selection of technologies

WP021
Content Document of evaluation of the technologies considered, provided with justification of the choice.
Due date 01/03/1999
Document../../files/OF021-001-Selection of theTechnology for Textur Mapping (COIN).doc

(Contents)

Coordination Committee defined

WP011
Content A person is be designated by each partner for the Committee
Due date 01/03/1999 Release date 28/02/1999
Document../../files/MG011-003-Report on the startup meeting.zip

(Contents)

Pilot users' requirements for the system

WP023
Content Document with the requirements from the pilot users: transactions retailer-supplier, e-catalogue, web sites, sale outlet layout; supplier IMS and order processing until the fabrics nesting system; the document deals with the data in the databases, the required functions, general layout of the sales outlet and of the software user interfaces, architectural and deployment constraints for the system.
Due date 01/05/1999 Release date 31/10/1999
Document../../files/OF023-001-User requirements for the Ishtar system.zip
Document2../../files/AD011-001-A possible Scenario of the final system.doc
Document3../../files/MG011-006-Report about the meeting in Munchen 14 and 15-10-99.doc

(Contents)

Overall system architecture

WP024
Content Document that describes the overall system architecture
Due date 01/07/1999 Release date 24/09/1999
Document../../files/OF023-001-User requirements for the Ishtar system.zip
Document2../../files/OF022-001-3964-34.doc

(Contents)

EDITEX document updated

WP022
Content An adaptation of the EDITEX standard to support the order of the made-to-measure garment has been formalized.
Due date 01/07/1999
Document../../files/AD024-010-ISH-FTX su Orders - MISURE1.xls
Document2../../files/AD024-011-ish-ORDERS1.xls

(Contents)

Architecture of the CMS system

WP022
Content A document defining the architecture of the CMS and the interface towards the e-catalogue system.
Due date 01/07/1999
Document../../files/OF022-001-3964-34.doc

(Contents)

Procedure for acquisition of the images of fabrics

WP022
Content A document defining the procedure to follow to acquire the images of the fabrics with related software tools. The document contains also the results of the tests on the real fabrics and the related images (about 120) on a CDROM.
Due date 01/08/1999 Release date 19/06/2000
Document../../files/OF022-004-Acquisizione Stoffe.doc
Document2../../files/OF022-005-Acquisition of Fabrics.doc

(Contents)

Design of the modules

WP024
Content The architecture and the functional design and the interfaces of all the database and modules.
Due date 01/10/1999 Release date 04/03/2000
Document../../files/OF024-001-Database8.zip
Document2../../files/AD024-016-Technical open issues.doc
Document3../../files/AD024-019-Order analysys disp ing (Hitman).doc

(Contents)

Measurement Assistants module (BMA)

WP026
Content Two groups of functionss in a module (BMA) to verify measurements, taken as difference/alteration on a reference model or taken directly on the body of the customer. This is a software
Due date 01/03/2000 Release date 09/09/2000
Document../../files/PR026-001-BMA-Sept2000.zip
Document2../../files/OF026-001-Features of BMA (Cad Modelling).doc

(Contents)

Texture mapping module

WP026
Content Module to be connected to the electronic catalogue to apply fabrics to the garment images. It is named WebPortrait. It is a software whose features are in the report the meeting in Bologna 20-21- july - 2000
Due date 01/03/2000 Release date 30/08/2000
Document../../files/MG011-012-Report bologna 20-21 july 2000.doc
Other linkhttp://render.ishtar.gruppocoin.it/render.asp?Model=FGL101&Fabric=10154-00520&Resolution=576x768

(Contents)

WEB site (FTP)

WP025
Content The front end for the IMS towards the retailers. It receives and send XML files with information about the fabric availability and the orders. It is FTP front end with a server that answer everytime that a message is left in the ftp area. It is a software and a server machine.
Due date 01/03/2000 Release date 06/10/2000
Document../../files/AD025-008-BOOKING-UNBOOKING NEW PROCESS (Hitman).doc
Document2../../files/AD025-001-Order and booking management in Hitman.doc
Document3../../files/AD025-007-XML FILES updated version (neosis).doc

(Contents)

Updated supplier's information management system

WP025
Content The internal Information Management System of the supplier is reorganised and can foresee the lead time, knows the fabrics availability, receives the EDI order from the WEB site, launches the production to the nesting subsystem. It is a software.
Due date 01/03/2000 Release date 05/05/2001

(Contents)

SW to obtain customised model from customer meas

WP025
Content It is a software that receives the body measurement and the CAD description of the standard models and develops a nesting plan for the customised garment. It is a new module of the FITNET software system of Lectra, named FITNET2. It is a software.
Due date 01/03/2000 Release date 30/09/1999
Document../../files/MM025-001-FITNET2 e BODYFIT- screenshots.doc

(Contents)

Data for the catalogue

WP026
Content Data for trial production and test in the field (more than 100 fabrics and 100 images of model of garment to which to apply them) for the two pilot sites. The document describes the material. The data are in the database.
Due date 01/03/2000 Release date 18/07/2000
Document../../files/TS026-001-Struttura sart I00 FLY.xls

(Contents)

Colour management system module

WP026
Content Module to be connected to the electronic catalogue to have a high quality of the image (faithful colours, device and viewing condition independence). It is a software.
Due date 01/03/2000 Release date 19/06/2000
Document../../files/PR022-002-appletsAll.zip
Document2../../files/PR022-005-ImageConv.jar
Document3../../files/PR022-004-CalibApp1.jar

(Contents)

E-catalogue

WP026
Content The electronic catalogue, with the browsing and the creation/management functions, and its packaging (like installation tool and draft user documentation). It is a software on CDROM. First release August 200 Second release November 2000 Third release May 2001 Fourth release July 2001
Due date 01/03/2000 Release date 30/11/2000
Document../../files/TS027-011-Videoconference of November 9 2000.doc
Document2../../files/MG011-013-Report of the meeting in Lisbon - October 2-3 2000.doc
Document3../../files/MG011-019-Report about VDC of February.doc

(Contents)

Plan of tests

WP027
Content Plan of all the tests to be performed defined at methodological level.
Due date 01/03/2000 Release date 01/11/2000
Document../../files/TS027-016-Plan of the tests.doc

(Contents)

Choice of the Automatic Measurement Machine

WP027
Content COIN decides if they want to deploy the Cad Modelling's Automatic Measurement Machine or if the market offer a better machine for their aims.
Due date 01/03/2000 Release date 12/05/2000
Document../../files/OF027-001-lettera benatti su 3D body scanner.doc

(Contents)

Customer database

WP026
Content Software to manage the customer database to store data about the customers and the orders (complete with the measurements). It is a portion of the backoffice. It is a software.
Due date 01/03/2000 Release date 05/09/2000
Document../../files/AD024-023-database structure updated.zip
Document2../../files/OF026-001-Features of BMA (Cad Modelling).doc

(Contents)

Courses for the personnel

WP041
Content Training courses promoted at the pilot sites of Coin, AlFerano and Hitman.
Due date 01/05/2000
Document../../files/MG011-021-Report about Final Meeting in Mestre 24-9-2001.doc
Document2../../files/MG043-001-Report about Munich 20-4-2001.doc

(Contents)

Reports about integration and functional tests

WP027
Content The document presents an overview about the testing activities and their results.
Due date 01/06/2000 Release date 30/09/2001
Document../../files/OF027-002-Summary of the result of the tests.doc

(Contents)

Brochures and poster and articles of magazines

WP051
Content Realised by the partners: general brochure on the project (Italian and English versions), brochure of the Coin Pilot site, many articles on magazines, a poster on Ishtar for fairs.
Due date 01/09/2000
Document../../files/DI043-002-Ishtar Coin Depliant.zip
Document2../../files/DI051-004-Depliant ISHTAR1 (ita).pdf
Document3../../files/DI051-008-FitNet-Description1 (Lectra).doc

(Contents)

Pilot site Alferano ready to start

WP042
Content The system is ready for trial activities regarding WEB and sale representatives channels at the AlFerano site. The pilot user has its own CD-ROM of the system.
Due date 01/09/2000
Document../../files/MG011-021-Report about Final Meeting in Mestre 24-9-2001.doc

(Contents)

Pilot site Hitman ready to start

WP042
Content The system is ready for trial productions of made-to-measure garments ordered through XML documents at the Hitman site.
Due date 01/09/2000 Release date 05/05/2001
Document../../files/MG011-021-Report about Final Meeting in Mestre 24-9-2001.doc

(Contents)

Pilot site Coin ready to start

WP042
Content The system is ready for trial activities regarding the shop channel and the EDI order sending at the COIN site. The pilot user has its own CD-ROM of the system. Hitman and COIN has an agreement about all the economic matters regarding the trial sales.
Due date 01/09/2000 Release date 05/05/2001
Document../../files/MG011-021-Report about Final Meeting in Mestre 24-9-2001.doc

(Contents)

Decision about copyrights and patent actions

WP031
Content The owners of the property rights on the hardware and software decide that no more actions should beo undertaken. The only protection is in the confidentiality of the information on the design. This is the result of many meetings where the IPR issues were debated.
Due date 01/09/2000 Release date 15/10/1999
Document../../files/MG011-006-Report about the meeting in Munchen 14 and 15-10-99.doc
Document2../../files/MG011-021-Report about Final Meeting in Mestre 24-9-2001.doc
Document3../../files/MG043-001-Report about Munich 20-4-2001.doc

(Contents)

Participation in at least 3 fairs

WP051
Content The fairs CEBIT and SAMAB
Due date 01/01/2001
Document../../files/DI051-009-samab (cad modelling-ita).doc
Document2../../files/DI051-015-Samab4- scanfit.jpg
Document3../../files/DI051-018-Participation in CEBIT.doc

(Contents)

Final report on the impact of the system

WP043
Content A report describing all the impacts of the system and its impact with real customer. The report describes the trial sales and contains also measurements of the impact, for example derived from questionnaires.
Due date 01/01/2001 Release date 30/11/2001
Document../../files/OF043-001-The Impact of the system.doc

(Contents)

Final version of the system

WP043
Content The final versions of all the modules is available on the pilot sites.
Due date 01/01/2001 Release date 30/09/2001
Document../../files/MG011-021-Report about Final Meeting in Mestre 24-9-2001.doc

(Contents)

Decision about further agreement on exploitatation

WP031
Content An updated Consortium Agreement, or specific inter-partner agreements, may address joint ventures and market division more effectively than the present one. If it is decided, a new agreement is established.
Due date 01/01/2001
Document../../files/MG011-021-Report about Final Meeting in Mestre 24-9-2001.doc
Document2../../files/MG011-009-Report of the meeting in Bologna (11-12 May 2000).doc
Document3../../files/MG043-001-Report about Munich 20-4-2001.doc

Found : 32