List of documents:

Third progress report

Addendum to the third progress report

 

 

Third Progress Report

(Third period: January 2000- June 30th 2000)

 

 

Overview

 

The third period of the project has been characterized by the completion of the design activities (WP 2.4) and the start up of the main tasks of development of the prototypes (WP 2.5 and WP 2.6). From the point of view of the scheduling of the activities the difficulties for one of the partner continued until the end of January and were only partially recovered in the following months.

 

In the period covered by this report the final design of the retailer side of the system was accomplished and the features of some prototype were discussed between the partners to validate the design solutions and to better support the innovative process of sales described in the user requirements. This activities has produced some revision both in the user requirements and in the design of the system

Meanwhile some activities started to disseminate the concepts and approach of Ishtar and they stimulated interest in the clothing/textile sector.

 

At the end of the reporting period the main achievements are:

-          the tools for colour management have been accomplished (images, applet, procedure)

-          the set of high quality images of the fabrics were scanned

-          release 1.0 of the texture mapping module was accomplished

-          release 1 and 2 of the Body Measurement Assistant were delivered

 

-          database design was delivered together with a first pre-release of the backoffice

-          the first two releases of the prototype for the electronic-catalogue module were delivered

-          the fabric booking/availability interface between retailers and supplier that is based on XML documents was realised and functionally tested .

-          a pre-release of the user manuals was delivered

 

-          the set of models and fabrics for the trial sales (and a part of the commercial agreements) was defined: (316 fabrics, 11 models of 9 jackets and 2 trousers)

 

-          the concepts of the system were presented to conference dedicated to the textile/clothing sector.

 

As in the previous report the planning of activities has a delay in respect of the initial workplan. In fact Neosis, that plays a relevant and critical role as designer and developer of the retail side prototype suffered for the lost of a part of its technical staff (in Portugal the liberalisation of the telephony and communication services produced a hard competition to gain the best ICT technician and the larger companies were more effective in their action).

This pause of activities in Neosis continued until a new staff were reorganised and the activities started in February. After, the delay about Neosis's tasks was partially recovered, but other points required more time than planned:

 

Furthermore, the translation of the user requirements and of the new sales process designed in the previous activities resulted a bit more difficult and took a lot of time, a specific care was dedicated to have a common comprehension of the process of sale before to translate it in a commonly accepted approach; secondly, some policies about concepts very market-sensitive (like prices policies) changed in the companies (Hitman) and required to change part of the specification and of the database structure.

This required a specific effort and the organisation of specific meetings and a videoconference. For this reason some of the tasks of design and validation required more resources than planned.

 

These and other more specific consideration convinced the pilot user company responsible for the shop channel of sales (Coin) to cancel from the planned activities the deployment in the shop of the 3D body scanner machine (this decision was planned in the WP 2.7). The system has the interface toward the machine but it will not be deployed in store for all the time of the trial sales. The possibility to realise a 'spot' deployment for some weeks will be considered after the first phase of tests, according with the constraints of the sales structure involved in the tests.

 

Finally the increasing interest in the XML technology and the, contemporary, lose of interest in technology such us EDI is inducing the partners to reconsider the approach of the order transmission between the retailer and the supplier; the use of EDI technology appears less and less to be able to guarantee the features of 'open and connectible' system that are one of the requirements of the project and an increasing interest is toward the XML solutions. This is a point that will be faced urgently in the next period of the project.

 

After June 30th a new meeting has been organised in Bologna and will be in the next report. However it is important to point out that there the partners decided to organise a videoconference about the first complete running version of the system that will be on September 12th and a meeting on September 28-29 focused on the trial sales activities. A second points will be the analysis and eventual rescheduling of the trial sales on the Internet and Sales representatives channels and all the remaining activities.

 

 

Detailed description of the activities

 

WP 1.1, coordination

A specific meeting dedicated to the e-catalogue module was organised in Lisbon on February; a general meeting had place in Bologna (11-12 May 2000) in the ENEA structures; and a videoconference was organised to demonstrate and discuss the first prototype of the e-catalogue module.

After the meetings reports (see references A, D, I) were produced with decision and the comments of all the partners.

The WEB site of Ishtar (http://server1.pisa.enea.it/ishtar) has been updated with new pages and updated information.

 

The harmonizing activities was pursued in the period, with a strong contribution to the production/circulation of documents and the planned scheduling has been adapted and reorganised to meet the evolution of the project. A specific goal was to create the conditions to recover the delay of the project maintaining the cohesion of the partners.

 

WP ended before this period:

-          WP 2.1, selection of technologies

-          WP 2.2, adapting available technologies

-          WP 2.3 customer and market requirements

WP 2.4, System architecture and design

Structure of the system

The hardware and software components of the system were established (defining the architecture and versions of the server, see reference A, I).

The overall system architecture was accomplished, the database was reorganised and the design was detailed (see reference B).

A specific attention was dedicated to the Customer database (re-named 'Backoffice' of the system) to help the management of the data both to load the catalogue and to monitor and manage the orders.

 

User interface (behaviour and organisation of the navigator module)

A lot of activities were dedicated to the logic organisation of the Interface and to optimise the appearance of models and fabrics (see reference C). A specific test page was realised in the Ishtar web site for simulating image sizes and user's behaviour (http://server1.pisa.enea.it/Ishtar/test/ippsa_Tests.asp).

In the Lisbon meeting (February) the graphical line of the interface was presented and finally approved in the meeting of Bologna (see reference I, J, K)

A simulator was realised with PowerPoint and presented in the videoconference (April 17th 2000, connecting Bologna, Mestre, Lisbon and Munich) to validate the navigation approach of the system (see reference G).

The policy of price (algorithms and data structure to calculate them were redesigned according with new needs of the pilot users.

 

Order and sizes process

The order processing system was detailed and the interface designed (protocols and XML data formats).

Further, the rules to check input errors and to test the body measures against the data about model sizes were re-thought; together with a new set of measurements that were also codified (see reference D).

Hitman has detailed the modification needed to support the orders though its internal information management system.

WP 2.5 construction of the prototype to process the order

The front-end system to receive and send information (XML files) for fabric availability and booking was realised, while the changes in the internal information system to automatically support the order process did not started. For this reason in a first phase of the trial tests, the system will require the action of human operators to activate the process (see references G).

The XML documents to realise booking and check availability were built and approved (see reference H).

WP 2.6 construction of the prototype for the retailers

This package was developed realising two release of the prototype of the retailer side of the system (model and fabric browsing, sizing, order construction) and working on the interface between this and the other modules (Body Measurement Assistant, Colour management system, Texture mapping, order processing) that are near to be accomplished.

A first version of the Texture mapping module has been accomplished, but some problems arising from the quality of images and the search for the optimisation between sizes of the images, effort to maintain the catalogue and faithful appearance of the textured models suggested to realise a second version that is under development.

The BMA module was accomplished but while inserting it in the system some problems of interface raised and now a third release is being developed.

The same happened for the calibration and visualisation applets that were accomplished and required to fix some bugs.

 

Presently the first pre-release is working in http://neoshop2.neosis.pt , it presently is connected with the BMA module and the colour calibration applet.

Analogously the first pre-release of the backoffice system is working at http://neoshop2.neosis.pt/ishman to help the industrial pilot user to upload the first set of data (please do not try to load anything it). Its interface will be reorganised to facilitate the uploading operations.

A part of the test data (data not related with the seasonal set of information about garment and fabrics) was uploaded in the system.

 

A pre-release of the user documentation has been written and used to test the Backoffice (see reference R).

WP 2.7 Functional and Integration tests

The functional and integration tests of all the modules have begun and revealed points to be fixed or enhanced.

We expect for the next reporting period to realise an intense activity of test.

WP 3.1

The partner established a framework that will be translated in a formal agreement about the maintenance and evolution of the system after the end of the project.

Neosis declares that they will sale systems that will be an adaptation of the Ishtar concepts to the needs of their customers and not an exact replication of the system.

The definition of a framework of co-operation between Neosis and Lectra to sale the whole system together appeared too much difficult because of the different sales approach of the two companies, while some co-operations could be established on a case-by-case basis.

Commercial basis were discussed for the trial sales and an agreement was written between Coin and Hitman, in the next future also Hitman and AlFerano should do the same.

WP 4.1, 2, 3 Training at pilot sites, Trial activities and adaptations

No more activities were undertaken before to have the final release of the system completely tested in the pilot sites.

WP 5.1 Action to promote awareness

On the technology side

Participation to the conference 'Internet Imaging' in San José (23 – 26 January 2000) to present the concepts of the architecture of the high quality image catalogue (a paper was published from that conference as reported in the previous report).

On the industry side

Participation (and presentation of the project) to a conference in the framework of the project Medressa (the only cost for the project were in labour, while the travel costs were funded by the Medressa project) in Egypt to promote European technology in the south of the Mediterranean Sea.

Participation to the international conference ITIT (Como, march 23-24th), organised by ASCONTEX, Italian centre of services for the Textile industries with the co-operation of Euratex (European association of Textile industries).

A first brochure to present the project has been prepared (see reference S).


Short report of the activities from the partners

ENEA

Organization of the meeting in Bologna and of the multipoint videoconference, participation to the meeting in Lisbon; monitoring of the discussion about the database and user interface organisation; activity of reporting and problem resolution; maintenance of the Ishtar web site supporting the project (http://server1.pisa.enea.it/ishtar).

 

 

Image quality:

Image architecture and development of the architecture for faithful representation of the fabrics:

-          setting up of specifications for the images and for the procedure to browse the images (together with Coin and Hitman)

-          definition and test with a simulator on the web of the concepts of the user interaction with the images of models and fabrics (http://server1.pisa.enea.it/Ishtar/test/ippsa_Tests.asp).

-          quality image scanning procedure, applet for the calibration of the monitor for internet user (without dedicated hardware), applet for faithful visualisation of images (through the subcontractor CNR-ITIM) (see reference L, P)

-          acquisition of a set of 140 images of fabric with three scale of resolution (through the subcontractor CNR-ITIM)

 

Further ENEA participated all the activities regarding design and validation of the system and the activities about the commercial agreement on the results of the project.

 

Dissemination
Participation to the conference 'Internet Imaging' in San José, participation the Medressa conference in Egypt (the only cost for the project were in labour, while the travel cost were funded by the Medressa project); ENEA also participated together with COIN (that presented the project in a speech) to the conference ITIT (the travel and labour costs of ENEA for this conference were not charged in this project).

Further ENEA promotes the made-to-measure concepts and the Ishtar project creating awareness with the participation in specific initiatives of the textile/clothing industries (Igofast conference, activities of projects involving the major Italian industries).

ENEA prepared a first brochure to present the project.

 

AlFerano GmbH

Target: implement pilot software platform for testing and training purposes

 

Project coordination work: participation in Bologna meeting. Report and presentation of status. Discussion about steps to take and necessary activities with respect to the timing of the project.

 

WP 2.3/6

-          coordination of the activities concerning the WP with the other partners

-          test AlFerano pilot WEB site

o        sum up of requirements and presentation to the partners

o        check up visual representation of products/garments via Internet

o        collect experience in e-business with tailor made products

-          negotiate commercial agreement with the project partners

 

Cad Modelling

In the six month in reference, has been turned the technical survey for the passage from a stand-alone configuration of BMA applicative – as it has been presented to the Partners at the Munich meeting – to a configuration operating in browser environment, to the realization of the real program.

This program has included a set of structural changes that has taken on account the migration to the different operative environment (IE5 and Netscape), as well as of some expressed exigencies by the Partners, in reference to a simply “transportability” and above all to the possibility to bring adjournments to the characteristic parameters of the measurements control system, as exposed later on.

 

The developed modules by Cad Modelling have been the following.

 

1.     Module for the manual introduction of the anthropometrics dates: user’s interface and guide for the body measurement taking (ref § 1.5 and part of the § 1.3 of doc. ADO-003Block-ben3(1).doc);

2.     Module of adequate anthropometrical measurements control (ref. § 1.1 of doc. ADO-003Block-ben3(1).doc);

3.     Module for Size and Drop search, “CERCATAGLIA/DROP”, in reference to the anthropometrical measurements (ref.  1.2 of doc. ADO-003Block-ben3(1).doc);

4.     Module of stand alone measurement and automatic Identification (ScanFit® system; § 0 of doc. ADO-003Block-ben3(1).doc);

5.     Module of Anthropometrical identification following the Classification method of Cad Modelling (ScanFit® system; § 0 of doc. ADO-003Block-ben3(1).doc);

6.     Module for local printing of the anthropometrical schedule.

 

In particular, for what concerning the point 1., in opposite to what originally foreseen by the project (module at charge of Neosis), Cad Modelling has asked to develop also this module  considering the fact that the interaction of this part with the other modules described at the points 2. 3. 4. 5. and 6. is very strong, and its development would be resulted optimised only if conduced in integrated way with these other parts.

This way, the macro module realized by Cad Modelling – that for convenience we call globally BMA and that includes what described in all the previous six points – interacts with the principal program (Navigator) through a record that identify the Customer using a customer_code given by the Server. This record contains all the anthropometrical information, that will have been digitised manually or, if present in the sales point, coming from the automatic system.

These measures will be subjected to the examination of the adequate control and CERCATAGLIA/DROP modules.

 

COIN

Activity  Description                                                                                                                                                       End date

 

 

2.4.3

2.4.7

 

Customer DB

This DB was often discussed with main Partners and remade  to satisfy information to be stored  and  to obtain the required simplicity.

The agreement was an acceptable compromise; activity recently ended has defined the minimum tools  and queries  necessary for  Customers’ Personal DB (data and access keys)  analysis  and maintenance.              

 

 

End of May

 

 

2.4.1

2.4.7

 

Orders (activity mainly in collaboration with  Hitman)

Many times Orders was  argument of discussion, not only for data but also for  different aspects regarding  information’s exchange  between Retailer and Supplier.

The work re-described  the information’s flow  and   re-analyses  some detailed aspects with particular attention to operations and time sequences. In details:

 

Fabric maintenance

Fabric availability verifications to be loaded at the beginning of the work-day and to be inspected during the day according to Garments selection, Colours simulation and sales activity

Fabric booking and un-booking

Fabric block  and un-block

-          Cleaning activities for non finished operation

-          Accuracy in defining the amount of fabric needed for “groups” of Garments and  consequently the  impact  on stocks.

 

Garment data

Discussions about  Tables and DB proposed by Neosis

The problem of “Price Table” and “Garment identification and Coding”.

-          Definition of different  logics for obtain the Sales Price in case of Jacket and in case of Suit

-          Garments  coding in respect of Gruppo Coin’s rules

 

Data flow for  Orders Operations.

Definitions and formalism for the use of FTP Server and Client to be used for stock verifications and stocks maintenance.

Samples of XML coding .

 

Order Transmission

Definition of principles for Order exchange between Retailer and Supplier

Redesign of Flat file and re-discussions about information to be send to Supplier

-          Order DB: description, design, most important items, management

-          Order flow verification – Order posted – Order taken

 

EDI transformation and annex: aspects that involve Orders in relation to XML that became a standard and that can overcome the necessity of EDI transformation. Respect of Standards.

 

 

Order DB: statistical analysis

Definition and samples of what is to produced as tool for the Orders’ portfolio analysis just for System  Administrator then for Sales Personnel.

 

 

End of May

 

 

 

 

 

 

End of June

 

 

 

 

 

 

 

 

 

End of June

 

 

 

 

 

End of June

 

 

 

 

 

This part is in progress

 

 

 

(in progress)

 

 

 

 

End of June

 

2.6

 

Catalogue

Review of Catalogue logics.

Definition of Images’ characteristics:

-          dimensions for thumbs nails

-          dimensions for standard image

-          dimensions for high definition and quality Images for Rendering Operations.

-          dimensions and characteristics of  Sketch’s images

Discussion about  layout pages and graphical aspects.

 

Garments Images

Acquisition of  digital images starting from real samples of garments sent by Hitman.

Activity for resizing images and tests for obtain the best quality according to different images’ dimensions.

Trial for better  scanning operations and images.

 

Fabric Images

Import of Fabric images produced by CNR-MI.

Trials and test of scanning  system and scanning quality regarding Fabrics.

 

 

End of March

 

 

 

 

 

 

 

 

Started in March and activity in progress

 

 

Same as above

 

4.1.16

 

Back Office (in collaboration with Hitman, ENEA and Neosis)

Participation to Back Office design and description.

Test activity and discussion . Proposed modifications and different solutions for some parts.

 

 

During May to the end of  June (in progress)

 

4.1.16

 

Navigator (in collaboration with Hitman and Neosis)

Participation to  the definition of logics and most important parts description.

Redefinition and deeply description of work flow for in shop activities.

Sectioning of the navigation.

 

 

February

May and June (activity in progress)

 

2.4.1

2.4.9

 

Measures (with Hitman collaboration) and Measurements

Revision  and collaboration  about  Measurement’s process and rules  defined by Hitman and  CadModeling.

Re-analysis of defined measures; we  add new  qualification codes for:

-          Group measures for show them on the same Navigator’s page

-          Define theirs sequence on the Navigator’s page

-          Assign mandatory flag.

 

Meeting with Cad Modelling for verify Scanfit Machine and the real possibility of installation into Coin’s Shops.

Valuation Activity to obtain impressions of use of this machine used by Other Retailers.

 

Discussions about some aspects of Measurement and Functionality of Software Modules developed by Cad Modelling.

 

 

From March to June

 

………

 

Rendering Software

Driving activity for obtain a real web-version of the “Portrait” software product.

Definition of rules, technical constrains, organisational aspects.

Test of the first version – decision of changing  launching commands – construction of ASP page to be inserted into Navigator.

Revision of logics and boundary of  the new software version to be developed for  remote Rendering Operation using Internet connections.

 

Internal organisational and technical difficulties of DGS (the third Party in this activity) have produced (in the past and fairly now) an anxiety  and critical impact  for the project.

Last dead line is at the end of July.

The product version that we use now is sufficient for our scope but, at the moment,  it’s not stable.

 

We directly developed different software modules for overcome DGS problems with the intention to speed up the whole project (for these aspects).

 

 

 

January

February

June

 

 

 

 

 

 

 

 

 

 

 

(activity in progress)

 

 

General Activity

 

General Project Activities

Intense mailing  activity  - discussions – exchange of documents and files.

 

Documents Preparation for and Participation to Bologna  Ishtar Meeting

 

Meetings with DGS about Rendering Software Product and annex problems

 

Different meetings with Hitman, Cad Modelling

 

Meeting Coin-Hitman : commercial people was involved for obtain agreement, solutions, compromises, planning, prices, support materials and responsibilities. 

 

 

 

during all the period

 

May

 

from Jan. to June

from Jan. to June

 

June

 

 

 

Promotion Activity

 

Ascontex Meeting in Como

Material and documents preparation for this Meeting and participation as Speakers for Ishtar Project 

 

 

 

23-24 of March

 

 

 

HITMAN

Activity from the document ACTIVITY                                                                                       End date

 

2.4.1        Sizing                                                                                                                                 30/05/2000  

                Discussion with COIN about sequence picture appear on the

                Definition of what field must be on the forms

                Preparation of list of Acronym for sizing entities according with Hitman industrial process

                new rules to obtain  the drop and stature from table CERCATAGLIA

 

                Orders and garment data

                Total revision of the DB for these entities. New rules to obtain price and cost for the Suits

 

2.5.5        Analysis and construction of the prototype for fabric booking                               25/04/2000

                With NIKOS company installation in Hitman of the FTP server

                and definition together with COIN of the transactions to update the

                availability database in Hitman.

 

                Meeting with COIN to discuss about customer database , acronym

                Construction and the XML files .                                                                                   24/02/2000

 

                Meeting with Coin  to discuss about the construction a parameter                         26/05/2000

                Field in the entity Acronym Model for drive the showing and

                The management the data for measures                                                                                                                                                                                                                                                                                                                                 

                Mailing activity  - translation – documents to prepare it .                                         30/06/2000    

 

2.6           Construction of the prototype for the retailers                                                            30/05/2000

                Validation together with COIN of the Catalogue Software and  of the

               Customer database , relation on this and reorganisation of the data.

 

                Meeting in CNR with Mrs Schettini to see the result on fabrics

scanning  with the Hitman technical expert about fabric.                                           02/06/2000

 

2.6.9        Preparation of the images of sketches model selected to send COIN                      30/06/2000

 

 

2.7.5        Trial transmission with NEOSIS of records about booking/unbooking,                  30/06/2000

                block/unblock of fabrics and update of the database on the server_ftp of Hitman

                Use the Navigator , trial logic flows , discuss  and redefine some

                Part of shop activities.

 

                Use of BackOffice to insert the data for catalogue                                                      30/06/2000

                Trial data for Fabric, Garments, configure, measure, CERCADROP table

                Arrange the data with COIN e NEOSIS , prepare data set to fill in

                Back office ( fabrics and CERCADROP table data )                                                                                                    

                At present again trial mode.

 

 

                Only for booking an so on , discussion with Nikos, Coin                                          30/06/2000

                Neosis  about result and transmission on the database on the

                Hitman server .

 

3.1

                Meeting with COIN people for commercial agreement about model

                Fabrics' price on so on                                                                                     07/06/2000

 

Lectra

In this period Lectra participated the meeting in Bologna but did not have specific tasks to outperform.

For this reason its cost statement is lacking in this report.

 

Neosis

 

Considerations

 

We had some delays in the ISHTAR project execution especially in the end half part of 1999. Some of those delays had a reasonable explanation in the 2nd project report. Problems related with the year 2000 consumed a huge percentage of Neosis' human resources. Technician’s scarcity made the work market much more aggressive and Neosis lost some important technicians in the last months of 1999 and early months of 2000. Simultaneously the recruitment of new IT technicians was difficult because there was a lack of people in the market, and the number of IT companies grew very fast, specially in the telecommunications sector. In the first half part of 1999 we had in Portugal 4 (four) telecommunication companies and by the end of 1999 we had 11 (eleven) ones, excluding the spin off of the first ones. Those companies absorbed all IT people available with very high salaries. 

 

Due to the above-described situation, in the third semester we allocated to ISHTAR a substantial NEOSIS IT work force trying to recover all the delays and we implemented additional working force in all work packages. Fortunately we have recovered a lot of time and parts of the developments are accomplished just in time for the retailers summer tests.  Because there are a lot of NEOSIS engineers working inside the ISHTAR project sometimes we have some problems in the integration modules process because we work faster than some of the other partners, becoming more difficult to recover time.

 

In the next points you can find detailed documentation in form of tables and schedules that describe the ISHTAR NEOSIS high activity during the semester object of this report. Some of this high activity will be continued during the 4 rd semester.

 

 

NEOSIS people allocated to the ISHTAR project

 

The following table shows NEOSIS allocate people in the project, the number of work hours of each person and its distribution in months.

 

Mrs Isabel Correia left NEOSIS in the end of March. Mr Carlos Carvalho ( carvalho@neosis.pt )  started working since 10 of May in NEOSIS and has had an active work in the project being responsible for the administrative procedures in the project. 

Also among the technical people some changes took place. Mrs Eunice Lee Silva left NEOSIS in January. At the same time Mr Joviano Silva substitute Mrs Eunice Lee. Mr Joviano ( joviano@neosis.pt ), analyst and system engineer, is responsible  for all it concerns  the data base design and XML modules. Mr Nuno Fonseca has started working since March and Mr Alexander Yip since  April. Mr Nuno Fonseca (nfonseca@neosis.pt ), analyst and system engineer, is the responsible person for the catalogues maintenance and development. Mr Alexander Yip ( ayip@neosis.pt ), analyst and system engineer,  is the responsible person for the Backoffice development and maintenance.

 

Some other people have participated actively in the ISHTAR project like Mr Sergio Santos, Internet Senior programmer. Mr Carlos Luz, Mr Pedro Correia and Mr Luis Filipe, all Internet developers, who were working and developing several things under co-ordination of Mr Nuno Fonseca and Mr Alexander Yip.

Mr Fernando Milhano ( fmilhano@neosis.pt ) Internet and E-commerce senior specialist, and Networking Engineer, is the official technical co-ordinator of this project in NEOSIS and has allocate 80% of its time in this semester to the ISHTAR project, designing, developing and co-ordinating the NEOSIS Ishtar activities.

 

 

 

 

 

 

Jan 2000

Feb 2000

Mar 2000

Apr 2000

Mai 2000

Jun 2000

Total

Project manager

 

 

 

 

 

 

 

 

 

Isabel Correia

30

15

30

 

 

 

75

Carlos Carvalho

 

 

 

 

20

30

50

 

 

 

 

 

 

 

 

Technical  Manager

 

 

 

 

 

 

 

Fernando Milhano

120

125

115

125

110

80

675

 

 

 

 

 

 

 

 

Technical people

 

 

 

 

 

 

 

     Eun. Lee Silva

58,50

 

 

 

 

 

58,50

Joviano Silva

104

135

135

117

135

78

704

Nuno Fonseca

 

 

84,5

117

135

135

471,50

Alexandre Yip

 

 

 

117

135

135

387

Sergio Santos

 

135

135

117

135

135

657

Carlos Luz

 

 

135

117

135

135

522

Pedro Correia

 

 

135

117

135

135

522

Luis Filipe

 

 

135

117

135

 

387

 

 

 

 

 

 

 

 

Total

 

 

 

 

 

 

4509

 

 

 

 

 

 

 

 

Table I - hour/man/month project allocation


3 . Allocation per project work package

 

The following table shows the allocation hour/man  per work package.

 

 

WP 2.3

WP 2.4

WP 2.6

WP 2.7

WP 3.1

WP 4.2

Total

Work in Previous Semesters

180

272

---

---

---

---

452

 

 

 

 

 

 

 

 

Project Manager *

 

42

64

18

 

1

125

 

 

 

 

 

 

 

 

Technical  Manager

 

416

227

30

 

2

675

 

 

 

 

 

 

 

 

Technical people

 

1070

2030

577

---

32

3709

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

180

1800

2321

625

 

35

4961

Table II - Allocation hour/man  per work package

Project manager allocation is based in the ratio of number of man/hour per package

 

 

Total Hours

Hours used

% of conclusion

WP 2.3

 

 

 

 

 

 

 

WP 2.4

 

 

 

     - Overall System Design Architecture

450

252

100 %

     - Design E-Catalogue

1050

976

100 %

     - Design Interfaces Cat towards

300

300

100 %

 

 

 

 

WP 2.6

 

 

 

   - Catalogue Sw development

1800

1691

94 %

   - Construction of  Customer db

300

160

53 %

-          Packaging of the application and 

       documentation

750

470

63 %

 

 

 

 

WP 2.7

 

 

 

  - Functional tests, measurement assistance ,cm, texture mapping, order system, supplier internal system

375

310

83%

  - Integration of the e-catalogue and cm/as/re n modules

225

200

89%

  - Integration test of the retailer side sub system

150

115

77%

 

 

 

 

WP 3.1

 

 

 

  -IPR- Analysis of cost/benefits about the copyright, protection of SW and HW

14

0

0%

 

 

 

 

WP 4.2

 

 

 

  - Ada – Adaptation of the electronic catalogue, customer db to the pilot site AlFerano

75

17

23%

  - Adc – Adaptation of the electronic catalogue and customer db to the pilot site COIN

75

15

20%

Table III - Total hours spend / Percentage of conclusion per package

4 . Detailed description of works in third semester

     Period between 02/01/2000 to 30/06/2000

 

WP 2.4 – ( System and design )

 

WP 2.4.1 – Overall system design architecture

 

NEOSIS has started working in this module since the end of 1999. But the major work ( 85% ) in this line of activities is to be done during this semester. Neosis spent a considerable time in this point because we needed to implement modifications and changes to initial definition of the user requirements. Some of these modifications were introduced after the Lisbon meeting in 10 and 11 of February. In this meeting important things concerned to Data Base design were changed and redesign after that.

At the moment this point is 100 % completed

 

WP 2.4.2 – Design E-catalogue

 

The architecture, on the retailer side, is designed to support the three system scenarios (Internet catalogue, Sales Shop Assistant, Sales representatives). It is our aim reducing excess, implement security of the transaction in a reasonable trade-off for costs and level of safety, to be modular and to comply, 100%, with a WEB / thin client architecture that reduce the maintenance and installation costs. The client works in a standard Internet web browser with some plug-ins and Java applets. The tools are state of art, and are developed using ASP ( Active Server Pages) as well as scripts and components. Because this, the system is perfectly tuned for Microsoft Internet Information Server 4.0 and 5.0. The portability is also present using ASP emulators for UNIX. These ASP emulators work faster than PERL CGI approach. Some additional work was spent in the web design line definition. The first approach to the web design line definition was made before in 1999, however difficulties in the definition of representative briefing of different retailers market were overcome in 2000. Neosis made this briefing based in several dispersed ideas from all the retailer partners. NEOSIS presented, at the Lisbon meeting, its new web design line definition.

Some additional work was made for the catalogue sales representative design, because the previous user requirements stated that this catalogue needed to use Microsoft Access database instead of Microsoft SQL Server. In order to implement off line work operation and synchronisation with the main server it is needed additional work design definitions and additional architecture.

NEOSIS also designed the ISHTAR BackOffice interface. This interface was designed to control and manage the ISHTAR catalogue. It allows, in a dynamic way, to define preferences, personalization, product categories, range of measures, etc., being based in the concept of independence between product categories. This BackOffice it’s designed in a way that allows each retailer to control 100% of its catalogue. After the meeting at Bologna 20 and 21 of May, all partners discussed a special need for catalogue collaboration, maybe, only in ISHTAR project.

In different languages the producer will be responsible to fulfil all data related with the products, description, images, etc. Each retailer using this data only needs to change the product price. For this special need we have to redesign the BackOffice in order to support different languages and currencies based in different databases. We maintained the initial concept of one catalogue to one BackOffice, because it is the only way to build a package totally independent and easily managed.

This point was 100% accomplished.

 

WP 2.4.3 – Design Interfaces Cat Towards

 

The ISHTAR interface architecture achieved, with a high degree of modularity allows the interactivity between the modules, and it was designed in order to have an electronic catalogue working with or without the modules of Colour Management, Measure Assistant, Texture Mapping, Order System and the Automatic Measuring Machine. In the final packing process, NEOSIS packed three different catalogues with the respective ISHTAR BackOffice: Sales representatives catalogue, Shop assistant catalogue and Internet Catalogue

This point was 100 % developed.

 

WP 2.6 – ( Construction of the prototype for the retailers )

 

WP 2.6.1 – Catalogue software development

 

This point had high priority in development proposes because the preparation of the catalogues data depended on the availability of tools resulting from this point. The considerable delay presented in this point, according with the submission propose, had a direct relation with the user requirement definition (WP 2.3) and the architecture design ( WP 2.4 ). The parallel developing of this point starting in March evolved considerable Neosis human resources. We didn’t recover all of the delay, but we have recovered a substantial part of it. This point is almost accomplished (94%). The Internet catalogue is accomplished and already working. The sales shop assistant catalogue is accomplished and already working in 1024 x 768 pixels resolution without the texture mapped module. This module was not available in the date of this report. The sales representative catalogue is accomplished and already working based in Microsoft SQL Server, however we need to migrate into Microsoft Access previous defined in the initial requirements. The ISHTAR BackOffice catalogue is developed and ready for tests and debugs. This ISHTAR BackOffice is full web enable and all function is supported using only a standard browser. With this we can reduce maintenance and enable the possibility of co-operative work. This is important because the manual process of a catalogue implementation is very exigent in terms of time consuming. In future ISHTAR catalogue exploitation, the ISHTAR BackOffice may be presented with some kind of redundant module because an ERP System can make the management of such catalogue. But this ISHTAR BackOffice found its target market in small medium companies with less knowledge and investments in IT systems. But we note that the open architecture of the ISHTAR system easily supports adaptations in order to work with external systems. Some changes are needed and they will be made in the first weeks of July after the changes in order to support several languages and currencies catalogues. At last, NEOSIS will provide two different BackOffice’s, one single catalogue other several language/catalogue.

Different kind of development is made using ASP components for integrate the XML modules in order to interchange information with the retailers BackOffice’s. The ISHTAR System uses the necessary components for booking fabric garments, to place orders and check its availability. In the design of this tools NEOSIS made an option to use DCOM objects, now called COM+ in Microsoft Windows 2000. The perfect integration in the Microsoft Windows Server architecture takes advantage of the last technology, optimising the use of resources of ISHTAR Server. We choose IIS/ASP as the front-end platform, for the accomplishment of the ISHTAR Pilot, with COM or DCOM as the framework component, respectively. This choice was motivated by the fact that the use of a Windows-based environment was already decided, and also because this type of front-end and framework is readily available in such an environment, and also widely supported by independent software vendors. The realisation of a DCOM interfaces between front-end and ISHTAR Core, as shown in figure 1, wasn’t accomplished without problems. IIS security settings seem to disallow a direct DCOM access, so that a local COM object had to be used as a front-end stub. Furthermore, this stub object must run in the context of Microsoft Transaction Server (MTS), at the same machine, in order to gain the required access permissions. The resulting architecture is outlined in Figure  below:

 

 

Figure 1 – Integration of Server-side ISHTAR Components

 

 

Neosis is actively working in the integration of these components making them simple in order to retailer’s use in future installation. Developments are almost done, however some tests are necessary to validate them.

 

WP 2.6.2 – Construction of customer database

 

Developments around this point are only 53% completed. The database design and all things related to the customer data store were already implemented. The presentation and the manipulation of this data are not developed yet, because they are less priority. However all information related to clients is stored and can support analytical single information views as well as crossed information views. It’s possible in future with right tools search to have a measurement system for customer preferences, their kind of personalization’s, kind of fabrics and materials, etc. Also out of the scope of this ISHTAR project phase is possible to link this database directly to CRM (Customer Relationship Management) System.

The beginning of the Interface development for this database is schedule for July 2000 and in August a great part of this point will be accomplished.

 

WP 2.6.3 – Packaging of the application and documentation

 

We need to develop several different packages, one per retailer. For The Internet catalogue we are developing the first packaging. For Sales Shop catalogue we wait for the texture-mapped system to implement it. For sales representative we need to wait for the integration of the MS Access database. The packaging of these catalogues is not easy because we need to install the system inside MS IIS (Microsoft Internet Information System) system. As a consequence of this, all the installation process requires a lot of Microsoft NT Server and IIS knowledge from the installer people. As for the manuals, the first version of the ISHTAR BackOffice is made, this is the largest manual because the BackOffice has a lot of interface. The catalogue manual presented and accessible via catalogue is 50% developed. The installation manuals are also in developing process now. Some of these documents are very expensive and require final refinements.

This point is 63% developed and NEOSIS hopes to accomplish it, during the month of July.

 

 

Wp 2.7 – ( Functional tests and integration tests )

 

WP 2.7.1 – Functional Tests, Measurement Assistance (cm), Texture Mapping,

        Order system, Supplier Internal System.

 

The system test will include a final check to ensure that the functional requirements have been properly translated into the system. Pilot users will have the final word about this subject. At the moment we have only made technical tests around all the system. A few problems were found inside the measurement module based in calculation error, and because this we spent some time trying to understand it, but the partner responsible for it, can solve the problem very fast. The tests with CMS were well succeeded. NEOSIS texture mapping subsystem was not available for test at the date of this report, despite all things are prepared for it. In what concerns the order system, it was tested internally according with the initial requirements. We are currently waiting for the final tests with the Retailer System. In what concerns the Supplier Internal System the tests with the booking, un-booking, actualisation, availability, etc, are running well. The test made between NEOSIS and Hitman related with the fabric availability and the interchange of the XML are almost finished and approved. Other things like booking and un-booking are developed and internally tested but waiting for the final partner’s validation.

This point is 83 % developed and the estimate date for its accomplishment it’s in the first half of July. 

 

WP 2.7.2 – Integration of E-catalogue and cm/ass/re n modules

 

A substantial part of developments concerned to this point are done, waiting only for the availability of Texture Mapped System. The integration of the E-Catalogue with the “cm” module is completed and works perfectly. The BMA (Measurement System) is integrated with the catalogue in the actual version. Some changes in BMA Module aren’t extremely necessary but welcome to the system, needing an extra work inside the integration process. This point is 89% accomplished and NEOSIS hopes to finish it in the first half of July.

 

WP 2.7.3 – Integration test of the retailer side subsystem.

 

Neosis proceeds with internal working simulation of each retailer catalogue using fictitious data information. Most of the tests are done, except the real tests after the installation inside each retailer server and with real data. We consider that 77% of NEOSIS tests in this point are done, but we need to wait for the installation process to complete it.

 

 

 

WP 3.1 – (Actions and agreement dealing with IPR)

 

WP 3.1.1 – IPR – Analysis of cost/benefits about the copyright protection of the software and hardware.

 

NEOSIS postponed the elaboration of this analysis for July, which will be presented in the next project meeting.

 

WP 4.2 – ( Adaptation, pilot sites, install and feedback )

 

In the initial definition it’s supposed that the pilot users catalogue is not able to customise the system. To reduce the risk of some problems, related with the integration inside internal Information Management Systems, etc., the system has tools that provide assistance to the customers in creation, management and customisation of the catalogue presented inside the ISHTAR BackOffice catalogue. Interface can be easily adapted because all catalogue interfaces are developed in HTML. The connection to the database is based in open standards as SQL and ODBC and easily adaptable to connections to third party application of the company Information Management System. For each pilot user NEOSIS provides a packaging pre customised compliant with each initial requirements. For this reason some of NEOSIS work in this point is based in building a packaging pre customised and after this it works in order to help solving installation problems and also as help desk and consultation services.

 

WP 4.2.1 – ADA- Adaptation Of The Electronic Catalogue To Customer DataBase To The Pilot Site AlFerano.

 

Based in the initial requirements AlFerano needs two catalogues with two different needs - Sales Representatives catalogue and Internet Catalogue. All the catalogues work connected to the same central server. The sales representative catalogue need to work in offline mode, because this is necessary an internal server working inside the laptop. Some special adaptations in each catalogue are made to reflect the initial requirements. AlFerano needs a server with hosting the Internet catalogue. Neosis provides the same catalogue hosting in our office. About the sales representatives, the problem is easy to solve because it is necessary only to run the set-up program for installing the applications inside the IIS system. Note that this sales representative uses a laptop running Microsoft Windows 2000-professional or Microsoft Windows NT workstation 4.0.

Neosis has pre build the first version of the Internet catalogue and a Sales representative version, but running in Microsoft SQL server.

 

WP 4.2.1 – ADA- Adaptation Of The Electronic Catalogue To Customer Database To The Pilot Site Coin.

 

The Coin site version of the catalogue, derivate from the Internet catalogue, but with texture mapped module active, plus some changes in the options zone in order to control the orders, status of orders, previous orders and all information about your clients. Also the BMA module has a different version for support the automatic size system machine.

 

 

4.6 –  Other NEOSIS activities in the ISHTAR project

 

                               Lisbon meeting

 

The Lisbon meeting in February 10 and 11 was organised by NEOSIS asked both by ENEA and NEOSIS. This meeting was very important because it clarified a lot of things about the requirement definition and helped to better tune the architecture design, especially in the database modularisation process. In this meeting we had the presence of ENEA, Hitman and NEOSIS. Mr Fernando Milhano, Mr Joviano Silva and Mrs Isabel Correia represented NEOSIS.

Videoconference

 

This videoconference was organised by ENEA and it’s happened in April 17th. During this videoconference NEOSIS presented the ISHTAR catalogue design to all partners and respective explanation and considerations about it. It’s possible to found our presentation in ENEA ISTHAR server. Mr Fernando Milhano, Mr Nuno Fonseca and Mr Joviano represented NEOSIS

 

 

 

 

 

Bologna meeting

 

This Bologna meeting took place in May 11 and 12 and it was well organised by ENEA. In this meeting several things were discussed and for the first time all modules were presented and all partners could contact with the project evolution. NEOSIS had an active participation in the subjects:

 

-  Live presentation of the catalogue navigation and discussion (Milhano)

 

- Presentation of the status of art of the order processing, sizing in the catalogue and of the interface with other modules (Milhano first speaker, Angotti, Benatti, Fuchs, Redaelli ).

 

- Commercialisation agreements (ENEA, Lectra, Neosis, Cad Modelling)

 

-  Planning of next activities.

 

Some things were changed in this meeting, especially in family suits. AlFerano and Coin decided not to use the capability of the system to choice different trousers for each suit. Also, inside the back office some changes were planned for accommodate the possibility of HITMAN filled an export data contents of the catalogue for each pilot user in national language. Other benefits and opinions were presented in order to improve better functionalities to the system.

Mr Fernando Milhano and Mr Joviano Silva represented NEOSIS in this meeting.

 

 

References of the report

 

A)     AD024-014-Report about the meeting in Lisbon revised 3.doc

B)      AD024-017 Database structure final

C)      AD024-016 Technical open issues on multilingual and image

D)      AD024-019 Order transaction analysis

E)       AD024-020 Report of the videoconference about the catalogue

F)       AD025-001 Order and booking management in Hitman ,

G)      AD025-002 Analysis of order construction and XML records,

H)      AD025-006 XML FILES for booking and availability

I)        MG011-009 Report of the meeting in Bologna (11-12 May 2000)

J)        MM024-008 Storyboard - Home page

K)      MM024-009 Storyboard - Select fabrics

L)       OF022-005 Procedure to scan fabrics (CNR ITIM)

M)    OF024-001 Database structure for filling

N)      OF026-001 Features of BMA (Cad Modelling)

O)      OF027-001 Decision about body scanner (COIN)

P)       PR022-002 Final colour applets

Q)      TS026-001 set of fabrics for trial sales

R)      US026-001/2 setup and user guides

S)       OF051-001-Ishtar in short.doc

 

 

Addendum to the Third Progress Report

(Third period: January 2000- June 30th 2000)

Integration to the Overview

About cost statements:

 

The cost of the personnel of Enea is subject to two events: the project is requiring a bit more of labour activities to be accomplished and the cost rate of some of the persons employed is raised.

 

The first one is due to the co-ordination effort that is stronger (and requires more qualified persons) than planned due to a multiplicity of factors, one of them is the management of the crisis of human resources of one of the partner and the recovering of all the related troubles, an other is the effort dedicated to the analysis and design of the sizing process (the same happened for the personnel of Cad Modelling that is engaged in the sizing process).

 

The second one is due to the career advancement of some of the people engaged in the project that changed their level of salary from the year 1998 to the year 2000. For this reason the average cost planned is resulted less then the actual average rate.

 

 

Integration to Short report of the activities of the partners

 

Lectra

 

In this period Lectra participated the general activities of the project (like the meeting in Bologna) and supported the activities of Hitman to test and evaluate the Fitnet 2 module. Improvements and refinements were adopted for the system in this period.